Cost Estimate Summary
Historic Pioneer Refinary
City of Santa Clarita
Task Low Cost Most Likely Cost High Cost Sour.ce
Preliminary Seismic Engineering $ 1,000 $ 1,200 $ 3,000 Consultant verbal estimate
Seismic Analysis of Existing Structures $ 13,800 $ 24,800 $ 46,800 Consultant verbal estimate
Prepare Scope for Rebuilt Structures $ 200 $ 700 $ 2,700 Consultant verbal estimate
Replicate Acid Treating Tank and Wash Tank platform $ 300 $ 800 $ 1,700 Internal Calculations
Design Ramps, Parking Lot, Entrance (ADA) $ 500 $ 1,500 $ 2,800 Internal Calculations
1
Purchase Placards $ 5,000 $ 6,000 $ 8,000 Sign Company verbal estimates
Interior Fencing $ 4,000 $ 4,200 $ 4,800 Verbal Quote from fencing company
Construction $ 24,000 $ 29,000 $ 48,000 Consultant verbal estimate
Restore Structures Included
Repair Foundations Included Above
1
Corrosion Cleansing $ 8,500 $ 9,400 $ 11,800 Verbal Estimate from Contractor
Realign Still w/crane $ 1,300 $ 2,500 $ 8,500 Internal Calculations
I
Brick Restoration $ 15,000 $ 20,000 $ 30,000 contractor proposal
Rebuild Missing Structures $ 59,000 $ 96,200 $ 104,200 Internal Calculations I
Install Trail $ - $ - $ Assumed Volunteer Work I I
Install Placards $ 300 $ 600 $ 2,000 Internal Calculations
I
Total $ 132,900 $ 196,900 $ 274,300 I
Chevron Commitment $ 15,000 $ 15,000 $ 15,000
Remaining Expenditures $ 117,900 $ 181,900 $ 259,300
CHEVRON MAKES NO WARRANTY, IMPLED OR
EXPRESSED, AS TO THE ESTIMATES PROVIDED
HEREIN. CHEVRON STRONGLY SUGGESTS THAT
THE CITY OF SANTA CLARITA SHOULD MAKE ITS
OWN DETERMINATION AS TO THE SCOPE of
WORK NECESSARY TO ACCOMPLISH THE GOALS
SET FORTH AND THE COST OF SUCH WORK
I
I
I
Cost Estimate1 .xlsSummary 1 /18/1998]